BBT East
400A Power Upgrade / Testing Station
This project consisted of bringing an additional 400AMP of continuous single-phase service to BBT East, BitsBeTrippin HQ. Our facility is a steel construction 80x40ft 3200sqft building hosting our front office, studio, work center for GPU/ASIC Repair and over 2000 sq/ft dedicated for indoor storage. Our work center required additional amperage for volume testing of ASIC miners along with bringing in enough electricity to support both a 50AMP travel trailer and a 12kw EV Charger from Ubiquiti. The site supports a total of 16 continuous ASIC miners at 240v operating at up to 20AMPs each, while charging an EV at 12KW and a Travel Trailer at 50AMP.
Total Planned Project Cost Estimation $20,000
Total Actual Project Cost $14,255
BBT Services Used
Our team handled project planning, coordination and pricing review with Power Company on upgrades. In addition, we handled the Dedicated Testbench construction, Network Expansion, Ubiquiti EV Charging Station Installation.
Our team coordinate the efforts of the Permits, Power Company and Electrician for a super easy 2 day installation of all of the mentioned activities.
Key Features:
400AMP Service Extension to Office (Power Company) Buried Service / Civ, Aluminum Service Extension /w Conduct
Upgraded Pole Transformer (Power Company)
400AMP Metering Cabinet (Power Company, installed by our Electrician)
Meter (Power Company, installed)
Twin 200 AMP Service Panels in Facility (Electrician)
8x 30AMP Breakers for L630 Plugs
1x 70AMP Breaker for Ubiquiti EV Station Pro
Dedicated Testing Bench with 8 Unit Support
208V Stepdown Transformer for lower voltage testing
277v Step up Transformer for increasing voltage for 277v testing
Network Expansion for testing using Ubiquiti 24 PRO POE
Cost Breakdown:
Power Company efforts - $6500.00
Electrician Parts / Labor - $4000.00
Ubiquiti EV Station Pro – $1300.00
Ubiquiti 24 Port PRO - $525.00
Cabling, Wire, Breaker – $675.00
208v Step Down Transformer – $500.00
277v Step Up Transformer - $725.00